Lesson 3.10.3

3.10.3 Managing strategic implementation Quiz: AQA Business, Unit 10

20 questions

In partnership with Revision Ninja

Lesson 3.10.3, Managing strategic implementation: 20 multiple choice questions for the AQA Business (7132), Unit 10: Managing strategic change, written with Revision Ninja.

Host it live on the board and students join with a game code on their own devices, or revise alone with Free Play. The answers are revealed in the game.

Host this setFree Play

The 20 questions

  1. What key role does leadership play during the implementation of a new strategy?

    • Manufacturing products
    • Providing direction
    • Setting tax rates
    • Auditing accounts
  2. What is the main benefit of clear communication during strategic implementation?

    • Lower interest rates
    • Higher import tariffs
    • Shorter product life
    • Employee alignment
  3. What is the primary role of organisational structure during strategy implementation?

    • Forecasting exchange rates
    • Calculating critical paths
    • Setting market prices
    • Assigning responsibilities
  4. What is the main purpose of network analysis in strategic implementation?

    • Calculating profit margins
    • Setting dividend policies
    • Scheduling complex projects
    • Measuring staff motivation
  5. In network analysis, what defines the critical path?

    • Highest float tasks
    • Lowest cost route
    • Shortest activity sequence
    • Longest time path
  6. What does total float measure in network analysis?

    • Minimum cost buffer
    • Earliest start time
    • Allowable activity delay
    • Total project duration
  7. In a network, activity A takes 3 days and has no predecessor. Activity B takes 2 days and follows A. Activity C takes 4 days and follows A. Activity D takes 1 day and follows both B and C. What is the duration of the critical path?

    • 6 days
    • 5 days
    • 8 days
    • 10 days
  8. Using the network in which A takes 3 days, B takes 2 days after A, C takes 4 days after A, and D takes 1 day after B and C, what is the total float of activity B?

    • 4 days
    • 0 days
    • 2 days
    • 1 day
  9. Which activities lie on the critical path in the network where A takes 3 days, B takes 2 days after A, C takes 4 days after A, and D takes 1 day after B and C?

    • A, B and D
    • B, C and D
    • A, B and C
    • A, C and D
  10. If an activity has zero total float, what does this indicate?

    • It is unnecessary
    • It has slack
    • It can expand
    • It is critical
  11. Why might a project manager amend a network diagram during project execution?

    • Fixed budgets set
    • Activity durations changed
    • Shares issued
    • Dividends declared
  12. Which metric is calculated when interpreting a network diagram?

    • Net profit margin
    • Return on capital
    • Earliest start time
    • Price elasticity
  13. Why must project managers closely monitor critical path activities?

    • Quality directly falls
    • Delays postpone completion
    • Float increases rapidly
    • Costs automatically rise
  14. What is a major cause of strategy failure during implementation?

    • High exchange rates
    • Excess total float
    • Poor communication
    • Low interest rates
  15. What is a key limitation of using network analysis in strategic implementation?

    • Relies on estimates
    • Ignores activity sequences
    • Guarantees profit growth
    • Removes all float
  16. How does effective leadership primarily support strategic implementation?

    • Setting interest rates
    • Calculating float time
    • Building employee commitment
    • Eliminating critical paths
  17. Staff are confused about roles following a corporate restructure. What was lacking?

    • Critical paths
    • Financial capital
    • Effective communication
    • Total float
  18. What is crucial when implementing strategy via cross-functional teams?

    • Maximising dividend yields
    • Inter-departmental co-ordination
    • Standardising prices
    • Eliminating all float
  19. An activity on the critical path is delayed by 3 days. How much is project completion delayed?

    • 3 days
    • 20 days
    • 6 days
    • 0 days
  20. How can a manager reduce the overall duration of a project using network analysis?

    • Extend dummy activities
    • Delay non-critical tasks
    • Increase total float
    • Shorten critical activities