Lesson DE4-DE6

DE4-DE6 Refining models, Gantt charts and resource levelling Quiz: AQA Further Maths, Unit 5

20 questions

In partnership with Revision Ninja

Lesson DE4-DE6, Refining models, Gantt charts and resource levelling: 20 multiple choice questions for the AQA Further Maths (7367), Unit 5: Optional application 3: discrete mathematics, written with Revision Ninja.

Host it live on the board and students join with a game code on their own devices, or revise alone with Free Play. The answers are revealed in the game.

Host this setFree Play

The 20 questions

  1. What type of diagram displays project activities as horizontal bars along a time axis?

    • Network diagram
    • Distance-time graph
    • Gantt chart
    • Resource histogram
  2. What chart shows total resource demand over time for a project schedule?

    • Precedence network
    • Resource histogram
    • Activity box
    • Gantt chart
  3. What process uses float to smooth out resource demand without delaying a project?

    • Resource levelling
    • Backward pass
    • Forward pass
    • Crash analysis
  4. What type of solution does a heuristic method produce in resource levelling?

    • Worst-case bounds only
    • Guaranteed optimal solution
    • Mathematically exact solution
    • Good but non-optimal
  5. How should a critical path model be refined if real-world resource availability is limited?

    • Add resource limits
    • Increase float times
    • Remove dependency arcs
    • Reduce activity durations
  6. Activities: A (3, no predecessors), B (4, none), C (2, after A), D (5, after B), E (3, after C and D). Workers: A 2, B 1, C 2, D 2, E 1, all started at earliest start times. What is the earliest time at which activity E can start in the early start schedule?

    • Time 5
    • Time 9
    • Time 4
    • Time 12
  7. In an early-start Gantt chart, how is total float typically represented for an activity?

    • Dotted arrow
    • Shaded box
    • Vertical bar
    • Line extension
  8. Activities: A (3, no predecessors), B (4, none), C (2, after A), D (5, after B), E (3, after C and D). Workers: A 2, B 1, C 2, D 2, E 1, all started at earliest start times. What is the peak number of workers needed at any time in the early start schedule?

    • 6
    • 4
    • 3
    • 5
  9. Activities C and D overlap between times 4 and 5. In which interval is peak demand?

    • Times 4 to 5
    • Times 0 to 3
    • Times 5 to 9
    • Times 3 to 4
  10. Activities: A (3, no predecessors), B (4, none), C (2, after A), D (5, after B), E (3, after C and D). Workers: A 2, B 1, C 2, D 2, E 1, all started at earliest start times. What is the total number of worker-days needed for the whole project?

    • 12
    • 27
    • 30
    • 24
  11. Why is a non-critical activity moved later within its total float during resource levelling?

    • Decrease duration
    • Reduce peak demand
    • Increase total float
    • Extend project length
  12. If peak demand is 4 workers but only 3 are available, what is the schedule?

    • Levellable
    • Critical
    • Optimal
    • Infeasible
  13. What happens to the overall project duration if a critical activity is delayed?

    • Float increases
    • Duration increases
    • Duration decreases
    • Duration stays unchanged
  14. During resource levelling without delaying the project, an activity must be shifted within what?

    • Its total float
    • Its worker allocation
    • Its late finish
    • Its duration
  15. What total float value is shown on a Gantt chart for a critical activity?

    • Positive
    • Variable
    • Infinite
    • Zero
  16. If a project model incorrectly assumes a worker can perform two parallel tasks, what refinement is needed?

    • Ignore overlap
    • Increase float
    • Add worker constraints
    • Reduce task durations
  17. What is the primary purpose of constructing a resource histogram in critical path analysis?

    • Identify resource overloads
    • Estimate activity costs
    • Calculate project float
    • Find critical path
  18. Activity D needs 2 workers for 5 days. How many worker-days does D require?

    • 5
    • 10
    • 2
    • 7
  19. Two parallel activities need 3 workers each, but only 4 exist. What action is required?

    • Halve worker demand
    • Combine both activities
    • Delay one activity
    • Cancel the project
  20. What is a key feature of heuristic resource levelling?

    • Gives practical schedules
    • Changes precedence relations
    • Guarantees optimal schedules
    • Ignores resource limits