Lesson 3D.4.1-3D.4.2
3D.4.1-3D.4.2 Activity networks and precedence tables Quiz: Pearson Edexcel Further Maths, Unit 38
20 questions
In partnership with Revision Ninja
Lesson 3D.4.1-3D.4.2, Activity networks and precedence tables: 20 multiple choice questions for the Pearson Edexcel Further Maths (9FM0), Unit 38: Critical path analysis, written with Revision Ninja.
Host it live on the board and students join with a game code on their own devices, or revise alone with Free Play. The answers are revealed in the game.
The 20 questions
-
In an activity-on-arc network, what represents each activity?
- dummy edge
- directed arc
- precedence table
- event node
-
What is the duration of a dummy activity in an activity network?
- one day
- variable time
- zero duration
- critical duration
-
What does a precedence table list alongside each activity?
- successor nodes
- immediate predecessors
- total float
- latest finish
-
A precedence table is used to construct
- a Gantt chart
- an activity network
- a linear programme
- a histogram
-
How is the earliest event time found in an activity network?
- direct sum
- average path
- longest path
- shortest path
-
How many finish events does a standard project network normally have?
- two finish events
- single finish event
- zero finish events
- multiple finish events
-
At what time can activities with no predecessors start?
- critical time
- time one
- time zero
- latest start
-
Activity A takes 3 days with no predecessors. Activity B takes 2 days and follows A. Activity C takes 4 days and follows A. Activity D takes 1 day and follows B and C. What is the minimum project duration?
- 7
- 8
- 6
- 10
-
Activity X takes 5 days and must be completed before activity Z, which takes 6 days. What is the earliest finish time of Z?
- 13
- 5
- 7
- 11
-
An activity of duration 4 leaves an event with earliest time 3, and an activity of duration 6 leaves an event with earliest time 2. Both end at the same event. What is the earliest time at that event?
- 10
- 8
- 6
- 7
-
Activity E depends on D, and D on C. Is C an immediate predecessor of E?
- No
- Always
- Partially
- Yes
-
A chain of four activities has durations 2, 5, 3 and 4 days, each following the last. What is the total duration?
- 12
- 14
- 15
- 10
-
Activities P and Q both start at time 0, with durations 4 and 7. Both must finish before X starts. What is the earliest start of X?
- 11
- 3
- 4
- 7
-
Event 0 has earliest time 0. Activity 0-1 takes 3, activity 0-2 takes 5, activity 1-3 takes 4 and activity 2-3 takes 1. What is the earliest time at event 3?
- 6
- 7
- 5
- 9
-
Activity B takes 3 days with no predecessors, and activity C takes 2 days and follows B. What is the earliest finish time of C?
- 2
- 8
- 3
- 5
-
Activities A (2 days, no predecessors), B (3 days, after A), C (4 days, after A), D (1 day, after B) and E (6 days, after C and D). What is the minimum project duration?
- 13
- 11
- 10
- 12
-
What is created in an activity network if a precedence loop occurs?
- Cycle
- Sink
- Float
- Dummy
-
Why do precedence tables list only immediate predecessors?
- reduces float
- creates dummy nodes
- avoids redundancy
- simplifies arrows
-
The finish event has an earliest time of 17. What does this represent?
- dummy duration
- minimum project duration
- maximum float
- critical count
-
Activities P (2 days), Q (5 days, after P), R (4 days), S (3 days, after R and P) and T (2 days, after Q and S). What is the minimum project duration?
- 11
- 9
- 10
- 7
Related quizzes
- Critical path algorithm Quiz · 3D.4.3 · 20 questions
- Total float and Gantt charts Quiz · 3D.4.4 · 20 questions
- Resource histograms and scheduling with workers Quiz · 3D.4.5-3D.4.6 · 20 questions
- Proof by mathematical induction Quiz · 1.1 · 20 questions
- Quadratic equations and complex arithmetic Quiz · 2.1-2.2 · 20 questions
- Matrix arithmetic and inverses Quiz · 3.1-3.2 · 20 questions
- Expectation of discrete random variables Quiz · 3B.1.1 · 20 questions
- The Poisson distribution Quiz · 3B.2.1 · 20 questions
- Geometric and negative binomial models Quiz · 3B.3.1 · 20 questions
- Hypothesis tests for the Poisson distribution Quiz · 3B.4.1 · 20 questions