Lesson 3D.4.1-3D.4.2

3D.4.1-3D.4.2 Activity networks and precedence tables Quiz: Pearson Edexcel Further Maths, Unit 38

20 questions

In partnership with Revision Ninja

Lesson 3D.4.1-3D.4.2, Activity networks and precedence tables: 20 multiple choice questions for the Pearson Edexcel Further Maths (9FM0), Unit 38: Critical path analysis, written with Revision Ninja.

Host it live on the board and students join with a game code on their own devices, or revise alone with Free Play. The answers are revealed in the game.

Host this setFree Play

The 20 questions

  1. In an activity-on-arc network, what represents each activity?

    • dummy edge
    • directed arc
    • precedence table
    • event node
  2. What is the duration of a dummy activity in an activity network?

    • one day
    • variable time
    • zero duration
    • critical duration
  3. What does a precedence table list alongside each activity?

    • successor nodes
    • immediate predecessors
    • total float
    • latest finish
  4. A precedence table is used to construct

    • a Gantt chart
    • an activity network
    • a linear programme
    • a histogram
  5. How is the earliest event time found in an activity network?

    • direct sum
    • average path
    • longest path
    • shortest path
  6. How many finish events does a standard project network normally have?

    • two finish events
    • single finish event
    • zero finish events
    • multiple finish events
  7. At what time can activities with no predecessors start?

    • critical time
    • time one
    • time zero
    • latest start
  8. Activity A takes 3 days with no predecessors. Activity B takes 2 days and follows A. Activity C takes 4 days and follows A. Activity D takes 1 day and follows B and C. What is the minimum project duration?

    • 7
    • 8
    • 6
    • 10
  9. Activity X takes 5 days and must be completed before activity Z, which takes 6 days. What is the earliest finish time of Z?

    • 13
    • 5
    • 7
    • 11
  10. An activity of duration 4 leaves an event with earliest time 3, and an activity of duration 6 leaves an event with earliest time 2. Both end at the same event. What is the earliest time at that event?

    • 10
    • 8
    • 6
    • 7
  11. Activity E depends on D, and D on C. Is C an immediate predecessor of E?

    • No
    • Always
    • Partially
    • Yes
  12. A chain of four activities has durations 2, 5, 3 and 4 days, each following the last. What is the total duration?

    • 12
    • 14
    • 15
    • 10
  13. Activities P and Q both start at time 0, with durations 4 and 7. Both must finish before X starts. What is the earliest start of X?

    • 11
    • 3
    • 4
    • 7
  14. Event 0 has earliest time 0. Activity 0-1 takes 3, activity 0-2 takes 5, activity 1-3 takes 4 and activity 2-3 takes 1. What is the earliest time at event 3?

    • 6
    • 7
    • 5
    • 9
  15. Activity B takes 3 days with no predecessors, and activity C takes 2 days and follows B. What is the earliest finish time of C?

    • 2
    • 8
    • 3
    • 5
  16. Activities A (2 days, no predecessors), B (3 days, after A), C (4 days, after A), D (1 day, after B) and E (6 days, after C and D). What is the minimum project duration?

    • 13
    • 11
    • 10
    • 12
  17. What is created in an activity network if a precedence loop occurs?

    • Cycle
    • Sink
    • Float
    • Dummy
  18. Why do precedence tables list only immediate predecessors?

    • reduces float
    • creates dummy nodes
    • avoids redundancy
    • simplifies arrows
  19. The finish event has an earliest time of 17. What does this represent?

    • dummy duration
    • minimum project duration
    • maximum float
    • critical count
  20. Activities P (2 days), Q (5 days, after P), R (4 days), S (3 days, after R and P) and T (2 days, after Q and S). What is the minimum project duration?

    • 11
    • 9
    • 10
    • 7

All Pearson Edexcel Further Maths quizzes