Lesson 3D.4.4

3D.4.4 Total float and Gantt charts Quiz: Pearson Edexcel Further Maths, Unit 38

20 questions

In partnership with Revision Ninja

Lesson 3D.4.4, Total float and Gantt charts: 20 multiple choice questions for the Pearson Edexcel Further Maths (9FM0), Unit 38: Critical path analysis, written with Revision Ninja.

Host it live on the board and students join with a game code on their own devices, or revise alone with Free Play. The answers are revealed in the game.

Host this setFree Play

The 20 questions

  1. Total float F(i,j) of an activity (i,j) is defined as

    • e_j - l_i + duration(i,j)
    • e_i - l_j - duration(i,j)
    • l_j - e_i - duration(i,j)
    • l_j - e_j - duration(i,j)
  2. What does the total float of an activity represent?

    • Minimum start time
    • Total activity duration
    • Required worker count
    • Maximum permissible delay
  3. What quantity is displayed along the horizontal axis of a Gantt chart?

    • Cost
    • Time
    • Total float
    • Worker capacity
  4. On a cascade Gantt chart, how is total float shown for an activity?

    • Dotted line
    • Shaded box
    • Vertical arrow
    • Solid bar
  5. A cascade chart is another name for a

    • Venn diagram
    • histogram
    • precedence table
    • Gantt chart
  6. Which event time determines the earliest start time of an activity?

    • Head event latest
    • Tail event earliest
    • Tail event latest
    • Head event earliest
  7. Which event time determines the latest finish time of an activity?

    • Tail event latest
    • Head event latest
    • Tail event earliest
    • Head event earliest
  8. An activity has earliest start e_i = 4, latest finish l_j = 12 and duration 5. What is its total float?

    • 5
    • 12
    • 3
    • 8
  9. An activity has earliest start e_i = 0, latest finish l_j = 6 and duration 6. What is its total float?

    • 12
    • 0
    • 6
    • -6
  10. An activity has e_i = 2, l_j = 7 and duration 3. What is its total float?

    • 7
    • 2
    • 4
    • -2
  11. An activity starts at its earliest time 3, lasts 4 and has total float 2. What is its latest finish?

    • 11
    • 7
    • 5
    • 9
  12. An activity has total float 5 and lasts 3 days. It is delayed by 4 days. What happens to the project completion?

    • No change
    • Project delayed by 4
    • Project delayed by 9
    • Project delayed by 1
  13. An activity has earliest start 5, duration 3 and total float 4. What is its latest start?

    • 8
    • 12
    • 7
    • 9
  14. An activity has e_i = 8, l_i = 10, duration 3, e_j = 11 and l_j = 12. What is its total float?

    • 0
    • 3
    • 1
    • 4
  15. An activity Y starts at its earliest time 4, lasts 10 and has total float 6. What is its latest finish?

    • 16
    • 20
    • 24
    • 14
  16. If one activity on a path uses its total float, what happens to float on that path?

    • Shared float increases
    • Shared float decreases
    • Shared float unchanged
    • Shared float doubles
  17. An activity has duration 6, earliest start 2, and its head event has latest time 9. What is its latest start?

    • 9
    • 2
    • 3
    • 1
  18. Activities A (time 0 to 3), B (time 1 to 5) and C (time 3 to 6) are drawn on a Gantt chart. How many are active at time 2?

    • 3
    • 1
    • 0
    • 2
  19. What is the total float of any critical activity?

    • Negative
    • One
    • Zero
    • Infinite
  20. An activity has earliest start 3, duration 4 and latest head event time 10. What is its total float, and is it critical?

    • 3 units, not critical
    • 3 units, critical
    • 0 units, critical
    • 7 units, not critical